Home  /  The Issues  /  Diesel & air

Backup generators, monthly test-runs, and what a chronic new source adds to an airshed already overloaded.

Most large data centers keep banks of diesel generators for backup, and where they do, those generators are test-run even when the grid never fails, typically monthly, releasing nitrogen oxides (NOx) and fine particulate matter. In a community already carrying a heavy pollution burden, that routine is the most consequential local air question. Beacon says its Calvert campus will have no diesel generators at all, a claim this page takes up below.

How to read this

We present each company's claim, then what the record adds. The counts below are working estimates where the exact figures have not been disclosed, and we flag which is which. Every claim traces to a named source.

What the record shows

The run-hour cap is what keeps the diesel banks from being a major polluter.

Edged's Atlanta facility runs Volvo Penta diesel generators. For the proposed Prichard site, MEJAC estimates as many as 15–25 generator units plus on-site diesel fuel storage, and expects it would require a "Synthetic Minor Source" air permit under the Clean Air Act. That permit category matters: a synthetic-minor source is one whose unrestricted emissions would cross the major-source line, but which accepts an enforceable cap on run-hours to stay under it. In other words, the run-hour cap is what keeps the diesel banks from being a major polluter.1,2

The independent evidence.

Backup diesel generators can emit 200–600 times more NOx than a natural-gas power plant per unit of electricity. A national review found nearly half of about 700 U.S. data centers sit in census tracts with above-median environmental burdens. Public-health modeling attributed roughly $6 billion in U.S. health damages to data-center-related air pollution in 2023, trending toward $20 billion and 600,000 asthma cases a year by 2028. In many regions the diesel runtime data centers are allowed "would trigger Clean Air Act violations in any other industry."2,3,4

Why it lands harder in Africatown

A chronic new source on top of an airshed already overloaded.

The Prichard site sits beside Africatown, which already hosts a dense cluster of permitted polluters: asphalt, chemical, cement, and pipe plants, the Hog Bayou methane power plant, highways, and rail. The question is not whether one source is harmful in isolation; it is what a chronic new NOx and particulate source does on top of an airshed already overloaded. And on the Gulf Coast, hurricanes mean extended grid outages, precisely when the generators run hardest and longest, in the worst conditions, near homes.1

How this applies here

Prichard and Calvert.

Prichard (Edged, ~6–8 MW). 15–25 units is MEJAC's working estimate; the exact count, ratings, fuel-storage volume, and run-hours are not yet disclosed. As of the June 11, 2026 community meeting the project was still at the pre-application stage. No ADEM air permit (or any other permit) had been filed, and Edged said it would hold off on permits until it had more neighbor buy-in. Every legally required public-comment point is still ahead.1,6

Calvert (Beacon, hyperscale). Beacon says the Calvert campus is "designed without backup diesel generators… no on-site emissions, smoke, or engine noise." If that holds, it is a real difference, from the Prichard proposal and from the company's own Kern County, California campus, which runs 15 × 2.5 MW of diesel. Two questions follow. First, what is the backup power for a round-the-clock hyperscale load, batteries, gas turbines, on-site generation, grid-only? None is disclosed. Second, "designed without" is a design intention, not a binding commitment: which permit or agreement would keep diesel off the site for its lifetime? No ADEM filing has surfaced either way.7,8

Questions a resident can ask

What to put to the company and the regulators.

01

How many generators, and how much fuel?

How many units, at what rating, storing how much diesel on site?

02

What is the enforceable run-hour cap?

What annual run-hour cap will the air permit impose, and is actual runtime publicly reported?

03

Are the cleanest engines required, and is monitoring public?

Are Tier 4 engines required, as Illinois began requiring for new data-center generators in January 2026, and is air monitoring funded and public?

Sources

Every claim, sourced.

  1. MEJAC, "Doing it Differently: Hard Earned Lessons from Engaging with a Proposed AI Data Center on the Africatown side of Prichard," 2026-05-26.
  2. Datacenternews.org, "Data Center Diesel Generator Permitting Explained," 2026; EPA New Source Review.
  3. Inside Climate News, "Data Centers' Use of Diesel Generators… Commonplace and Problematic," 2025-11-12.
  4. "The Unpaid Toll," arXiv 2412.06288; EDGI, communities near data centers.
  5. Encino Environmental; ALL4, "Data Centers 2026 Look Ahead" (Illinois Tier 4 requirement).
  6. "How Large Industrial & Data-Center Projects Get Approved in Mobile County and Prichard": pre-application status per MEJAC, June 2026; ADEM Air Permits (Ala. Admin. Code Ch. 335-3-14).
  7. Data Center Dynamics, "Canada's Beacon DC targets 275MW data center campus on California oil field," 2026-06-24 (15 × 2.5 MW diesel at Golden Valley / Kern County).
  8. Beacon Data Centers, "Calvert Infrastructure Hub" campus page (published 2026-06-12, updated 2026-06-30): "The site is designed without backup diesel generators. As a result, there are no on-site emissions, smoke, or engine noise." Company statement, uncorroborated by any public filing. beacondatacenters.com